State of Connecticut Paving Schedule for Route 7/Danbury Road

State of Connecticut Paving Schedule for Route 7/Danbury Road

The State of Connecticut is planning to mill and pave Route 7/Danbury Road from Wolfpit Road (State Route 106) to Wilton High School’s North Entrance (north of Catalpa Road). 

Milling work will begin on or about Monday, June 5th.  This portion of the work will take approximately 2 weeks (weather permitting).

Paving work will begin on or about Sunday, June 18th.  This portion of the work will take approximately 3 weeks (weather permitting). 

The daily hours of operation will be from approximately 7:00 pm to approximately 5:30 am.

The State of Connecticut will have an inspector on-site.

If you have immediate questions, please reach out to the State inspector on-site or call (203) 389-3035.